Antrim Fitness Forum, Antrim

mha were employed by Antrim and Newtownabbey Borough Council in October 2021 to undertake a two phased contract:

Phase 1 – Refurbishment of existing gym, provision of dance and spin studio with consideration to acoustics. Major refurbishment of w.c areas.  Provision of new roof covering to forum building.

Phase 2 – Major refurbishment works to village changing area, works to existing pool, resin flooring and ceiling upgrade.

Choice of materials on this project were critical due the chlorine environment.

mha appointment: Project Manager, Architect and Principal Designer

Proposed date for completion:  February 2024

Visuals supplied by JW Visuals

Share the Project with Others:
big fish casino daily limit reached
lamp-of-infinity
online-casinos-echt-geld
miracle-nutritional-cbd-sugar-free-gummies
where-can-i-buy-hazel-hills-cbd-gummies
does-shark-tank-weight-loss-gummies-work
keto-genesis-acv-gummies-near-me
top-rated-male-enhancement-reviews
herbs-blend-for-male-enhancement